Contact Energy & SIE Major EC&I Project – Te Mihi 2A

November 3, 2026

Earlier this year, Stanley Instrumentation & Electrical (SIE) was awarded the EC&I installation contract for the WK321 Wellpad at Contact Energy’s Te Mihi 2A Power Station Project. We’re pleased to share that the project has since been completed. This was a significant milestone for our team, and one we’re genuinely proud to have delivered.

The Te Mihi 2A project forms part of Contact Energy’s broader geothermal expansion. The WK321 Wellpad accepts Separated Geothermal Water (SGW) from Te Mihi 2A and Wairakei Station, feeding it to three reinjection wells. This critical infrastructure is designed to perform for 30 years with minimal maintenance.

Industrial equipment on a raised metal platform in front of a factory building.

What SIE delivered

Our scope across the WK321 Wellpad, T42 Hut, 303 Hut, and WAC Building covered the full EC&I installation package, including:

  • DCS panels & electrical DBs – Installation, glanding & termination
  • Cabling & cable support – LV, instrumentation, fibre & Profibus
  • Field instrumentation – Calibration & installation
  • Earthing & lightning protection – Full earth mat & bonding systems
  • General power & lighting – Internal & external across all buildings
  • Pre-commissioning & support – Through to process commissioning

The project also involved integration with ABB’s 800xA DCS platform, connecting Profibus, Modbus and Ethernet communications across the wellpad and steam field facilities.

Contact Energy Partnership

At SIE, this is exactly the kind of work we do best, technically complex, high-quality installations where precision and reliability aren’t optional. Geothermal energy is a cornerstone of New Zealand’s renewable future, and we’re proud to play a part in supporting Contact Energy’s continued investment in that infrastructure.

Contact Energy:

“We’re investing in new geothermal generation as part of our strategy to lead New Zealand’s renewable energy future. When we’re building new energy infrastructure at this scale and complexity, it’s as much about the people and partnerships we build along the way as it is about delivering industry leading energy solutions for Kiwis. SIE worked alongside our team from day one and impressed us with their approach, from planning right through to successful commissioning of the WK321 Wellpad.” Dyani Boyce – Contact’s Project Director Te Mihi 2.

SIE Project Lead:

“This was our first project with the Major Projects team at Contact Energy which involved 90% of our team at SIE, everyone worked in very well with each other including all contractors on site and overcame any issue as a team without any major setbacks. The organization from the Major Projects team made this happen with co-ordination meetings and great communication. Our team is proud of how the project went overall but especially the commissioning of the well pads and associated equipment as everything went very smooth and took less than 2 days to have the wells up and running. A lot of this was possible due to the pre-works our team completed.” Matt – SIE Project Lead.

We thoroughly enjoyed working alongside the Contact Energy team to deliver a result the whole project can be proud of.